| Construction Progress |
|
In response to growing demand, and in an effort to further improve the efficiency of our logistics, Vigon is in the process of constructing a 30,000 square foot distribution center complete with state-of-the-art warehouse and logistics management technology. Take a look at where we are now with this project, where we have been, and just think about where it will take us! |
|
August 25, 2008
After receiving the CO a few weeks ago, we have begun to move product from our existing warehouse to the new DC. Tom McKain from our Logistics Team, is seen here beginning to fill the new racks.
.
|
|
|
July 29, 2008
The installation of the In-Rack Foam Fire Sprinkler Grid is in progress. The sprinkler system will have a biodegradable solution injected to create foam fire suppression, enhancing its effectiveness.
.
|
|
|
June 18, 2008
The exterior finish work continues with the front entrance canopy being completed as well as the finish layer for the driveways and parking lot.
.
|
![]()
|
|
June 10, 2008
The Ribbon Cutting and Dedication Ceremony for the Joseph P. Somers Distribution Center was held with a number of state and local dignitaries as well as local media in attendance.
|
![]()
|
|
The Dedication Plaque |
![]()
|
|
June 2, 2008
Now that the initial layer of macadam base has been laid, the landscaping is being completed.
|
![]()
|
|
May 30, 2008
The paving of the parking lot and driveways is almost complete. The initial 4 1/2 inch macadam base course has been laid and the final top course will be applied after the landscaping has been installed.
|
![]()
|
|
May 6, 2008 The finish work on the interior continues with the cement floor sealant being applied to the loading dock area (shown) as well as the warehouse section of the DC. The next step for the interior will be the installation of the tile floors in the lobby, offices, bathrooms, and cafeteria.
|
![]()
|
|
April 30, 2008 The landscape retaining walls at the building entrance have been completed as well as the exterior grading of the parking lots and driveways. The next step for the exterior will be final inspections before the paving begins.
|
![]()
|
|
April 14, 2008 As the exterior grading work around the Distribution Center is nearing completion, the construction focus on the interior is on the framing and construction of the interior offices, locker rooms, bathrooms, and cafeteria. |
![]()
|
|
April 7, 2008 The final exterior grading and installation of stone sub-base is being completed in order to prepare for the construction of the various drives and parking lots.
|
![]()
|
|
March 27, 2008 Vigon's electrician Mark Borger, is busy finalizing the installation of a state-of-the-art computerized lighting panel which will automatically manage and control the lighting system within the Distribution Center.
|
![]()
|
|
February 19, 2008 With the exterior construction complete, and the interior floors poured, interior construction, electrical, and plumbing has begun.
|
![]()
|
|
November 5, 2007 Now that the exterior Distribution Center wall construction is nearly completed, the installation of the roof has begun. The next step after the roof is complete will be to begin pouring the interior concrete flooring. |
![]()
|
|
September 21, 2007 The decorative split-face cement blocks which will form the bottom portion of the Distribution Center walls are currently being put in place. Once the block portion of the wall is complete, the insulated steel panels will be installed on the upper portion of the wall.
|
![]()
|
|
September 7, 2007 The floor sub-base is in place and the steel erection is in progress. The steel being placed is for half of the building structure. .
|
![]()
|
|
June 22, 2007 Now that the additional blasting that was required to prepare the building base is complete, we have begun to form and pour the concrete for the base footings. These footings will support the exterior columns and walls as well as the flooring for the building. .
|
![]()
|
|
April 12, 2007 Now that the installation of the controlled fill sub-base is near completion, we will begin ground probing to determine if additional blasting will be required for the underground utility services as well as for the building footings.
|
![]()
|
|
March 12, 2007 We have begun to clear and stage for future use, much of the original topsoil on the site. This is being done to make way for shipments of controlled fill which will form a stable base for the installation of the footings, foundation, and pavement.
|
![]()
|
|
March 2, 2007 Now that the initial blasting has been completed, a retaining wall is being completed with the Cap Rock from the blasting ledge on the property.
|
![]()
|
|
February 23, 2007 The blasting is continuing on the site. To view a video of the blast in the picture click here. |
![]()
|
|
February 15, 2007 The site is quiet today due to the snowstorm we had yesterday but the new fallen snow sure looks nice!
|
![]()
|
|
February 12, 2007 Blasting has begun in order to begin pouring the footings for the new building.
|
![]()
|
|
February 2, 2007 Steve Somers and Dennis Dittrick review the building plans now that the site has been cleared, the water retention system is in place, and the ground has been broken for the building.
|
![]()
|
|
December 15, 2006 Now that the trees are gone, construction of the water retention system begins.
|
![]()
|
|
November 15, 2006 The process of clearing the trees on the site begins.
|
![]()
|
|
June 7, 2001 Once it was determined that the various buildings on the site are unusable and unsafe, they are torn down immediately.
|
![]()
|
|
May 21, 2001 Steve Somers contemplates the viability of utilizing some of the original buildings on the site.
|
![]()
|
|
April 16, 2001 At the beginning, the Vigon Distribution Center was just a field of dreams….
|
![]() |